Oct 28,2022
Melbourne Project Update: 500 Bourke Street
Project Udate: 500 Bourke Street
500 Bourke Street Update
Demolition – office tower strip out & ground plane structural demolition are rapidly approaching completion and thereafter demobilisation of demo contractor – always a positive milestone.
Facade rectification work progressing well
Good safety compliance as captured on both internal & external audits
New starter Alex Favaloro – welcome aboard! Alex has settled in quickly and is having a positive impact to the team
Hazmat removal approaching completion – high level of stakeholder interactions required
Services rough-in to tower floors progressing well – finishes to follow
Management of existing floor deflections and existing screed remains intensive
Resolution reached on a number of Latent Conditions and client issues, including FRV Approvals and Underpinning to B1
Management of live retail tenancies ongoing and to the satisfaction of all stakeholders
New site office on Level 1 approaching completion.